2025 subsidence works

2026 subsidence works

Restoration of a 15th-Century Timber Barn: Structural Stabilisation and Subsidence Repair


This project involved the careful refurbishment and structural stabilisation of a late medieval timber-framed commercial barn of approximately 500 sqm. The building exhibited progressive movement attributed to long-term subsidence, localised ground softening, and deterioration of primary load-bearing timbers at low level.


Initial Assessment and Movement Analysis

A full structural survey identified differential settlement along the north and east elevations, with the most significant movement occurring in two central bays. The original oak sole plates had suffered advanced decay due to prolonged ground moisture exposure, resulting in a loss of bearing capacity and uneven load transfer into the primary post-and-beam frame.

Secondary deformation was observed in the form of racking within several bays, with slight rotation in the principal tie beam assemblies. While the upper frame remained largely intact, the lower structural zone had effectively become the failure point of the building.


Temporary Works and Stabilisation Strategy

Before any permanent intervention, a full temporary propping system was installed internally to arrest further movement. Adjustable steel acrow props and spreader beams were used to support the principal load paths, allowing controlled redistribution of forces during repair works.

This phase was critical in isolating the unstable ground-bearing elements while maintaining the integrity of the historic frame above.

Installation of Load-Bearing Plinth System

Given the extent of timber decay at ground level, a decision was made to introduce discreet concrete plinths at key structural nodes. These were positioned directly beneath primary posts following careful laser-level survey work to re establish correct datum lines across the structure.

Each plinth was cast in reinforced concrete and finished below ground level where possible to minimise visual and environmental impact. A separation layer was introduced between timber and concrete using breathable isolation pads to reduce moisture transfer and allow for minor seasonal movement.

The original posts were carefully jacked and re-aligned before being lowered onto the new supports, effectively transferring load away from compromised sole plates while preserving as much historic fabric as possible.


Timber Repair and Frame Reconstitution

Where sole plates and lower post sections were beyond repair, targeted timber splicing was carried out using seasoned oak, matched in species and grain orientation to the original fabric. Traditional scarf joints, reinforced with concealed stainless steel fixings, were used to maintain continuity of load transfer while ensuring long-term durability.

In several bays, minor realignment of braces and secondary members was undertaken to correct historic distortion caused by uneven settlement.


Final Structural Outcome

The completed works successfully arrested ongoing subsidence and re-established a stable load path throughout the structure. The introduction of discreet concrete support elements, combined with traditional timber repair techniques, allowed the barn to retain its historic character while achieving modern structural reliability.

The building now operates as a hybrid system: a preserved medieval timber frame supported by a carefully engineered foundation strategy designed to respect both the material limits of the original construction and the environmental conditions of the site.


Site Manager Roy Holland : "It was nice to work on a very unique and traditional building, the detail and extent these old building were built to is incredible, the team enjoyed saving the structure for years to come"


Subsidence works enquires:

 

James Williams

info@avendale.co.uk

0207 971 1488

www.avendale.co.uk

 

Avendale is a leading international construction group. We finance, build, refurbish and maintain diverse, complex, buildings and infrastructure in the UK and the Middle East. Our constant innovation and business development provides the foundation to support our clients, creating a trusted reliable transparent journey towards their project goals. Avendale is trusted by some of the largest companies and organisations in the world to repeatedly deliver results on time and in budget.

by Glyn Meredith 30 April 2026
2025/26 Commercial Fire Damage Reinstatement Central London
by Glyn Meredith 30 April 2026
2026 Reinstatement Works in Surrey
29 April 2026
Avendale secures £2 million Façade Replacement and Remediation to major broadcasting facility
29 April 2026
Commercial re development 2026
29 November 2024
Energy efficiency underlines Avendale’s roof work 2025
8 October 2024
Avendale continues cladding works in Berkshire
8 October 2024
Cladding remediation 2023-24
8 October 2024
Heritage reinstatement works
17 September 2024
Fire reinstatement works in Mortimer Fire reinstatement and fire protection works remain high priority for Avendale in 2024. Our Mortimer fire reinstatement project sets an example of ambitious plans to save a badly damaged old commercial use property.  Close communications with loss adjusters saw this successful CAT A reinstatement through in a matter of months.
17 September 2024
Essential refurbishment works in Wokingham town centre  Wokingham town centre has seen significant investment and redevelopment, winning an award in the Economy prosperity category 2020 for the ambitious project that saw 215 new homes, highways improvements, pedestrianised community spaces and large landscaped park.